Skeleton Workplan for CanCore and ACCMD: 2005-2006

Plan Objective To outline the timelines, teams and approaches to developing the IMS ACCMD/CanCore Guidelines.

Outcomes/Deliverable Complete guidelines on ACCMD implementation in keeping with the CanCore guidelines, including these sections where applicable:

Element Name and Number

Size, Order, Value Space, DataType

Explanation (from IMS ACCMD specification)

Summary of Guidelines

Detailed Comments and Recommendations

Technical Implementation Notes

Vocabulary Recommendations

Plain Text Example

XML Example

NOTE: We are currently (24/10/05) starting with: CanCoreAccmd/AltToVis_Draft.doc - Draft document for ACCMD AltToVisual elements.

Project Scope

This project plan will be limited only to the development of the guidelines described in the Outcomes/Deliverables above. It will not include other work.

Project Team

The project team will be comprised of CanCore participants. This team will be a somewhat organic and malleable group but will include as central participants:

Norm Friesen Anthony Roberts Pierre Bernard Karin Lundgren Liddy Nevile Jutta Treviranus Anastasia Cheetham Andy Heath Nigel Ward David Weinkauf Joseph Scheuhammer Others? Please add your name!

The project team will operate as a cooperative group and strive towards consensus whenever possible. When consensus is not possible, a majority decision of participants during any monthly meeting will be considered appropriate in decision making.

Timeline Third Quarter 2005 (July-September)

Primary Class draft document

Equivalent class draft document

Fourth Quarter 2005 (October - December)

AlternativestoVis. & color classes draft document

AlternativestoText class draft document

AlternativestoAuditory class draft document

Begin translation into French

First Quarter (January - March 2006)

Final English version of all documents

Complete French translation

Dependencies

Translation is dependent on completion of guidelines [BR] Final version for first quarter 2006 dependent on completion of precious draft versions